Pune Ring Road Eastern Corridor: Construction Gathers Pace

Eastern Pune's game-changing ring road is finally rolling—here's the real progress, package by package.

Explore Now

Pune Ring Road Eastern Corridor: Latest Package-Wise Progress

Pune's much-discussed Outer Ring Road is no longer just a promise on paper—the eastern stretch is now visibly under construction, even as it trails behind its western counterpart. The eastern corridor of the Pune Ring Road has been divided into seven packages, of which work is currently underway on four, while the remaining three are awaiting administrative approval. For homebuyers and investors tracking connectivity-led growth on Pune's eastern flank, this staggered rollout is an important signal of how fast the corridor's real estate potential will actually materialise.

On the ground, progress remains at an early stage but is measurable. PRR-E1 (11.85 km) under Megha Engineering stands at 16% complete, PRR-E2 (13.8 km) with PNC Infratech has reached 17% progress, PRR-E3 (21.2 km) awarded to Megha Engineering is 14% completed, and PRR-E4 (24.5 km) with Roadway Solutions has touched 25% progress. By comparison, the western corridor is moving faster, with PRR-W1 at 19% (up from 16%) and PRR-W2 at 31% completed (up from 28%), underscoring the gap between the two sides of the 136-km ring.

The overall project remains firmly on the state government's radar. The ambitious 136-kilometre-long infrastructure project, being executed by the Maharashtra State Road Development Corporation (MSRDC), aims to decongest Pune city roads, divert heavy and long-distance traffic away from urban areas, and improve connectivity across the city's rapidly expanding peripheral regions. Speaking in the state legislature, Public Works Minister Dada Bhuse confirmed the phased approach for the pending packages: tenders for the pending eastern packages will be finalised before May 2026, with construction expected to begin by October 2026.

Timelines for full completion have also been laid out more clearly than before. Revenue Minister Dada Bhuse informed the state Assembly that the western section of the Pune ring road is targeted for completion by May 2026, while the eastern section is expected to be completed by May 2028. To keep the project on track, Chief Minister Devendra Fadnavis has directed that there be monthly reviews of permissions, land acquisition and construction progress, a move aimed at cutting delays that have historically plagued the ring road.

In a major development this month, the eastern side of the project got an unexpected boost beyond the original seven packages. Pune's Ring Road project has received a major boost after the Maharashtra Cabinet's Infrastructure Committee approved the eastern extension of the project, aimed at reducing traffic congestion in Pune city and diverting inter-state and long-distance traffic away from the city, with a revised project cost of ₹10,502.36 crore approved. This new extension is distinct from the original eastern packages and covers additional ground. The eastern extension includes a 39.605-km access-controlled expressway between Soratapwadi (Valti) on the Pune-Solapur Road and Varve (B.) (Shirve) on the Pune-Satara Road. The Maharashtra State Road Development Corporation (MSRDC) will undertake the construction, with the project planned for completion by June 2029.

Beyond raw kilometres and percentages, the eastern corridor's progress matters because of what it unlocks around it. Rapid urbanisation, expansion of industrial areas, new residential projects, growth of the IT sector and the rising number of vehicles have led to persistent congestion on Pune and Pimpri-Chinchwad's major roads. Once functional, the eastern packages and the new extension together are expected to change commute patterns for residential belts near Hadapsar, Wagholi and Loni Kalbhor. On public transport, the government is also examining complementary connectivity: the technical feasibility of the proposed Hadapsar–Loni Kalbhor metro corridor will be examined, with the corridor expected to significantly improve public transport options in eastern Pune and adjoining rural areas.

For homebuyers evaluating projects along the eastern periphery, the takeaway is nuanced. Construction is real and monitored monthly at the top level, but the four active packages are still in single or low double-digit percentage completion, and three packages haven't even been tendered yet. That means near-term traffic relief is unlikely, but medium-term appreciation potential around upcoming interchanges remains a genuine consideration for anyone buying in Pune's eastern growth corridor between now and 2028.

Narrative

SMART WORLD Projects

SMART WORLD Moshi
Upcoming

SMART WORLD Moshi

Moshi, Pune

2, 3 BHK • Price on Request

Smart World's North Pune debut

Smart World Shewalwadi
Upcoming

Smart World Shewalwadi

Shewalwadi, Pune

2, 3 BHK • Price on Request

Upcoming high-rise homes in East Pune

Smart World Hinjewadi Phase 3
Pre-Launch

Smart World Hinjewadi Phase 3

Hinjewadi Phase 3, Pune

2, 3 BHK • Price on request

Resort-style living in Pune's IT corridor

Smart World Pune
Pre-Launch

Smart World Pune

Talegaon-Chakan Belt, Pune

2, 3 BHK • Price on Request

1 km riverside promenade & golf-inspired greens

Smart World Pune - Hinjewadi Corridor
Pre-Launch

Smart World Pune - Hinjewadi Corridor

Hinjewadi, Pune

2, 3 BHK • Price on Request

Golf-course-facing homes on NH48

Smart World Pune - Wakad
Pre-Launch

Smart World Pune - Wakad

Wakad, Pune

2, 3 BHK • Price on Request

Riverside homes with golf-inspired greens

Smart World Sector 111 Floors
Pre-Launch

Smart World Sector 111 Floors

Sector 111, Dwarka Expressway, Gurugram

2.5, 3.5 BHK • Price on Request

Low-rise floors on Dwarka Expressway

Smart World Sector 128
Pre-Launch

Smart World Sector 128

Sector 128, Noida

3, 4 BHK • Price on Request

73-acre pre-launch on Noida Expressway

Book a Visit

Schedule Your Visit

Back

Quick Answers

What is the current status of the Pune Ring Road's eastern corridor?
Work is currently underway on four out of seven packages, with construction progress ranging between 14% and 25% depending on the package. Three remaining packages are still awaiting administrative approval and tendering.
When will the eastern corridor of the Pune Ring Road be completed?
The eastern section is officially targeted for completion by May 2028, while the western corridor is expected to be ready earlier, around May 2026. These timelines were confirmed by Public Works Minister Dada Bhuse in the state Assembly.
What is the newly approved eastern extension of the Pune Ring Road?
The Maharashtra Cabinet's Infrastructure Committee has approved a separate 33.8-39.6 km eastern extension between Sortapwadi on the Pune-Solapur Road and Varve-Shivare on the Pune-Satara Road, at a revised cost of ₹10,502.36 crore, targeted for completion by June 2029.
Which contractors are building the eastern packages?
PRR-E1 and PRR-E3 are being built by Megha Engineering, PRR-E2 by PNC Infratech, and PRR-E4 by Roadway Solutions. Each package covers stretches ranging from roughly 11.85 km to 24.5 km.
How will the ring road affect real estate in eastern Pune?
Improved connectivity along the eastern corridor is expected to ease congestion and open up new residential and commercial corridors near areas like Hadapsar, Wagholi, and Loni Kalbhor. However, actual price uplift typically follows once construction visibly progresses closer to completion.
Is the entire Pune Ring Road being built by one agency?
Yes, the Maharashtra State Road Development Corporation (MSRDC) is the executing agency for the ring road, including both the western and eastern corridors and the newly approved eastern extension.
Why is the eastern corridor behind the western corridor in progress?
The western corridor packages were awarded earlier and are progressing steadily, while several eastern packages are still pending tenders and approvals, creating a staggered implementation timeline across the two sides.
What is being done to prevent further delays on the project?
Chief Minister Devendra Fadnavis has directed monthly reviews of permissions, land acquisition, and construction progress to improve coordination between departments and resolve bottlenecks faster.
Will the ring road connect with any metro projects?
A proposed Hadapsar–Loni Kalbhor metro corridor is being examined for technical feasibility to complement the eastern ring road and improve public transport in the region.
Should homebuyers wait for the ring road to be completed before investing nearby?
Not necessarily. Early-stage infrastructure announcements often precede price appreciation, so buyers evaluating eastern Pune corridors may benefit from tracking package-wise progress rather than waiting for full completion.

For information only — this is not an offer and creates no obligation. Prices, layouts, and photos are indicative and can change anytime. Do your own verification before making a decision. About · Projects